How much has the Washington Bridge closure cost so far? We broke down the numbers.


PROVIDENCE − How much has the Washington Bridge closure cost the state, Providence and East Providence, three months after the fact?

East Providence and Providence have been paying extra for police details to deal with traffic, but Providence has an extra wrinkle: damage to city streets caused by semi-trailer trucks.

Most recently, Gano Street was temporarily shut down to fix a water main broken under the road.

Between Providence and East Providence, $400,857 has been paid so far. Add in the money the state has spent since the end of February, and it rises to $1.43 million.

Providence expects to need to repave

In Providence, the biggest single expense so far has been marine details, followed by police overtime and details and then public works. The total expenses so far are $124,878.

Construction on the closed side of Washington Bridge.

The city has asked the state to “support” the repaving of roads being slowly destroyed by heavy vehicles detoured because of the closure, but there are no estimates on what that will cost, Providence Police Department Spokeswoman Lindsay Lague wrote in an email.

Providence’s total costs so far are:

  • $51,573 for police overtime and detail pay

  • $70,305 for police marine details

  • $3,000 for public works, engineering and traffic engineering

East Providence sees ongoing detail expenses

In East Providence, the biggest expense, and the only one that is ongoing, is police details to deal with traffic. That expense is being reimbursed by the state.

Unlike Providence, East Providence has not seen major impacts on local streets from heavy semi-trailer truck traffic.

In all, East Providence has spent a total of $275,979 so far. That breaks down to:

  • $39,627 for the fire department (first week of closure)

  • $13,557 for schools (ongoing expense)

  • $9,213 for Department of Public Works (first week of closure)

  • $213,580, for police (reimbursed by the state)

How much has the state spent?

The last estimate for how much the state has spent was $1.03 million, as of Feb. 23, Department of Transportation Spokesman Charles St. Martin wrote in an email.

No new calculations have been provided.

Thanks to our subscribers, who help make this coverage possible. If you are not a subscriber, please consider supporting quality local journalism with a Providence Journal subscriptionHere’s our latest offer.

Reach reporter Wheeler Cowperthwaite at wcowperthwaite@providencejournal.com or follow him on Twitter @WheelerReporter.

This article originally appeared on The Providence Journal: The Washington Bridge closure is costing thousands in police overtime

Signup bonus from $125 to $3000 | Signup now Football & Online Casino

0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

You Might Also Like: