What were the cranes doing by the building collapse near Boise Airport? What we know


When a crane and the frame of an unfinished building collapsed near the Boise Airport Wednesday, killing three and injuring nine,much of the information released was fuzzy at best.

A crane was working on the airplane hangar for Jackson Jet Center. Did it fall on the building? Or did the building collapse on top of it?

Authorities still aren’t saying. But a growing bank of details outline what happened and when.

Perhaps the most significant new information about the crane comes from its operator, Boise-based Inland Crane. Vice President Jeremy Haener said the company was hired to help build the jet hangar and had finished most of the work Wednesday afternoon. Workers moved three of its four cranes off the job site, leaving the last one to place an end truss, which is a part of the roof.

“When the building collapsed due to an unknown structural failure, the crane boom — the hydraulic arm of the equipment — snapped on impact,” Haener said in a news release.

That rebuts early speculation that the crane fell first and caused the building frame to collapse. Hainer said no evidence pointed toward the crane operators or the crane itself as the reason for the collapse.

Haener said none of the Inland Crane employees were injured.

The U.S. Occupational Safety and Health Administration, or OSHA, has taken over the investigation from Boise authorities. That investigation may take months.

Haener said the collapse of the steel hangar broke the crane’s hydraulic arm, seen here in center bent out of place.

What about other factors?

Brian Rigby, president of Local 732 of the Ironworkers Union that covers Montana and Idaho, told the Idaho Statesman that documents showed that there “was definitely enough room in there to safely facilitate four different cranes.”

Rigby, who is based in Montana, said there’s a little more risk with multiple cranes than with one at a work site, but there are other ways the collapse could have started.

Considerations like wind and weather, good concrete, and making sure anchor bolts haven’t been moved or modified are major factors involved in safety, Rigby said.

“In a collapse, there had to be a force that was introduced,” Rigby said.

No members of the union were working at the Jackson Jet Center site, he said.

Wreckage of the future Jackson Jet Center hangar shows twisted girders with a crane in the center. Three were killed in the accident, and nine others hospitalized when the frame collapsed.

Wreckage of the future Jackson Jet Center hangar shows twisted girders with a crane in the center. Three were killed in the accident, and nine others hospitalized when the frame collapsed.

OSHA: Stop work when wind gusts reach 20 mph

Guidelines published by OSHA for cranes say that if wind speeds, sustained or in gusts, exceed 20 mph at the personnel platform, then a “qualified person must determine if, in light of the wind conditions, it is not safe to lift personnel.”

If it is not safe, the lifting operation must not start or must stop if already in progress, according to OSHA.

The National Weather Service in Boise recorded a 20 mph gust at the airport about 10 minutes before emergency services were called for the hangar collapse, according to prior Idaho Statesman reporting.

Other safety factors to take into consideration include side-loading, which can happen when a crane operator lifts a load that is not centered, according to Pennsylvania-based crane builder Spanco. This can cause a load to start swinging.

Rigby said the crane was a “run of the mill small crane” and nothing like the tower cranes, which dot downtown Boise.

Mobile cranes, like the ones used on the hangar, generally use a telescoping arm and can move around the job site. Static cranes, such as tower cranes Boiseans see when big new buildings go up downtown, are normally built on the job site and stay until construction finishes.

What qualifies a crane operator?

There are a few types of certifications to become a crane operator, with different types offered for certain kinds of cranes or operations.

The standard and most widely accepted certification is through the National Commission for the Certification of Crane Operators, or NCCCO, according to Illinois employment agency Industrial Trade Services.

Requirements for NCCCO certification include being 18 or older, passing a 90-question multiple-choice test in 90 minutes, and operational exams to show proficiency. Candidates must pass the written test and at least one specialty, 26-question exam.

Certifications are valid for five years, and candidates must finish all recertification requirements during the 12 months before the expiration date.

Uncertified workers operating cranes on-site could be faced with a maximum penalty of $16,131 per violation, according to OSHA. More fines could be tacked on for repeated violations.

Historic downtown Boise building condemned by city for ‘dangerous’ structural issues

Save this historic building, a Boisean pleads. We want to, city says. What just happened

The Idaho Sporting Goods store was a Boise icon. It’s now been demolished. This is why

Changes coming to 2 popular blocks in the heart of downtown Boise. Here’s what to know

Signup bonus from $125 to $3000 | Signup now Football & Online Casino